Mine Feasibility Research

Mine Feasibility Research
Product Detailed
Related Categories:Other Ore
Support of a project Based on the resource, market, policy and so on factors Offer a report Professional mining institute

Yantai Jinpeng Mining Machinery CO., LTD

Add:No.11, Fuzhou Road, development District, Yantai, Shandong Province

Tel: 0086-0535-3975297                 Fax: 0086-0535-3975297

Following  are a catlog of a research report.

Chapter 1. Pandect

1.1 Project general situation

1.2 Design basis&principle

1.3 Project construction condition

1.4 Main construction scheme

1.5 Public auxiliary facilities and civil engineering

1.6 Environmental protection and safety -hygiene

1.7 Investment and economic effect

1.8 Existing problems and suggestions

Chapter2.  Market analysis

2.1 Overview

2.2 Gold production statistics

2.3 Gold price analysis

2.4 Market analysis

2.5 Market forecasting

Chapter 3.  construction scheme research

3.1 Scale of development and service life

3.2 Product solution

3.3 Site plan

Chapter4. resources conditions

4.1 Overview

4.2 Sketch of regional geology

4.3 Geological and mining geological features

4.4 Deposit hydrogeological and mining technical conditions

4.5 Mine geology exploration work and its evaluation

4.6 Geological resources and reserves estimation

4.7 Infrastructure, production prospecting 

4.8 Existing problems and suggestions

Chapter 5. Ore mining

5.1 Mining areas

5.2 Mining technology conditions

5.3 Ore mining

5.4 Mine scale,work system and production capacity test&verify

5.5 Pioneering transportation system

5.6 Ventilation system

5.7 Mine filling

5.8 Underground watersupply, drainage and waterproof

5.9 Blasting equipment warehouse

5.9 Infrastructure project and project construction progress5-41

5.10 Existing problems and suggestions

Chapter 6. Mining machinery

6.1 Underground transportation system

6.2 Ming slope ascension 

6.3 Blind slope

6.4 Ramp lifting transportation

6.5 Compressed air facilities

6.6 Underground drainage

6.7 Underground water supply facilities

6.8 Ventilation system

6.9 Filling facilities

Chapter 7 Benefication

7.1 Overvieww

7.2 Raw ore

7.3 Benefication test

7.4 Comparation ofdesign scheme

7.5 Construction scale, service life and work system

7.6 Selection&calculation of main process equipment

7.7 Building layout and equipment configuration

7.7 Auxiliary facilities

7.8 Tailings facilities

Chapter 8. Assembly drawing transportation

8.1 Overview

8.2 Main facilities composition and the general arrangement

8.3 Enterprise cover area

8.4 Enterprise transportation and the factory road

Chapter 9. Civil and public aided engineering

9.1 Civil engineering

9.2 Watersupply and drainage

9.3 Electric power, telecom , instruments and automatic control

Chapter 10. soil and water conservation

10.1 Construction project and the surrounding environment situation

10.2Construction project control responsibilities scope

10.3 Discharge waste stone soil, waste of soil and water loss and cause&harm

10.4 Water&soil loss prevention plan

10.5 Restore vegetation work schedule

10.6 Guarantee of soil and water conservation measures

Chapter 11. Energy saving

11.1 Design basis&principle

11.2 Design of energy saving measures

11.3 Energy consumption indicators and analysis

Chapter 12. Environment protection

12.1 Overview

12.2  Main pollution sources and control measures

12.3 Estimate of environmental protection measures investment

12.4 Environmental management and monitoring

12.5 Soil-water conservation and land reclamation

12.6 Assessment of environmental impact

12.7 Suggestions

Chapter 13. Safety and hygiene

13.1 Overview

13.2 Design basis&principle

13.3 Analysis of main harm factor to production safety

13.4 Safety technical measures taken in design

13.5 Analysis of mining safety deposit reliability

13.6 Reliability of mining power supply system

13.7 Industrial hygiene

13.8 Safety and hygiene supervision and management systems and institutions set

13.9 Problems needed to explain

13.10 Special investment estimate

13.11 Construction project labor safety and hygiene beforehand assessment

Chapter 14. Organizations and fixed personnel

14.1 Set of the organization

14.2 fixed personnel

14.3 Plant schedule

11.4 Wages

14.6 Worker source and training

Chapter 15. Investment estimation

15.1 Investment estimation

15.2 Engineering survey and total investment

Chapter 16 Technical economy evaluation

16.1 Overview

16.2 Project total financing and use

16.3 Cost estimation

16.4 Production and income

16.5 Income determination

16.6 Financial profit ability analysis

16.7 Uncertainty analysis

16.8 Comprehensive economic effect assessment